Edwards Boulevard Sidewalk Project

Sidewalk Upgrade on Edwards Boulevard Loop

An aerial map highlighting a planned sidewalk project in red.
Photo Courtesy of SGM, Inc

We’re thrilled to announce that Edwards Metropolitan District has planned and is set to begin the repair and upgrade of the sidewalk along the Edwards Boulevard loop! Located adjacent to Edwards Village Boulevard and Homestead Drive, this project will replace the aging sidewalk with a brand-new, 6,000-linear-foot concrete walkway. The upgrade has been designed to improve pedestrian safety and accessibility, enhancing the community’s ease of movement. Stay tuned for more updates on this exciting enhancement!

New Sidewalk Project Welcomed

One of the newest and most used of the improvements completed by the Edwards Metropolitan District is more than a mile of new sidewalks throughout Edwards.

The $2 million project took two construction seasons to complete, said project manager Deron Dircksen, of SGM Engineering.

The new sidewalk replaces an old patchwork of sidewalks along Edwards Village Boulevard and Homestead Drive.

One of the most important elements in Dircksen’s view is the safety improvements installed near the Edwards Elementary.
They include safer crossings of Meile Lane, a fence and sidewalk on the east side of the school to help separate children and vehicles. Dircksen said the contractor, Gould Construction and the Metro District worked closely with the school district to resolve some of the safety issues at the school.

“Now a bike posse of kids can get to school safely” Dircksen said. All the improvements add to the safety for kids.”

On addition to the hard surfaces and some curb and gutter work some areas are being revegetated and reseeded he said.

Behind the scenes there was a lot of surveying, mapping and engineering that was done prior to construction beginning.

Construction workers, heavy machinery, and landscaping work in progress.
Photo Courtesy of SGM, Inc

Project and Updates

As of July 11th, 2024: Notable work completed and milestones met include: Approximately 40% of sidewalk improvements have been completed. On schedule: Substantial Completion: Monday August 26th, Final Completion: Tuesday September 24th. On budget

As of May 23rd, 2024: Edwards Metropolitan District Sidewalk Replacement project will begin construction Monday June 3. Construction is anticipated to last approximately three months. Any questions, please contact Deron Dircksen @ 970-384-9012

 Bidding

As of April 5th, 2024 the bid was awarded to Gould Construction.

Edwards Metropolitan District has partnered with BidNet as part of the Rocky Mountain E-Purchasing System to post bid opportunities to this site.  As a vendor, you can register with the Rocky Mountain E-Purchasing System and be sure that you see all available bids and opportunities. By selecting automatic bid notification, your company will receive emails once the Edwards Metropolitan District has a bid opportunity that matches your company's business. In addition, the site handles bid opportunities, RFPs, and RFQs for other member governmental agencies throughout Colorado.

The Edwards Metropolitan District looks forward to providing you with more bid information and simplifying the entire bid, proposal, and quote processes for everyone involved.  We appreciate your cooperation and welcome your participation.  If you need help registering, please call the Vendor Support department toll free 1-800-835-4603 option #2.

Link to Edwards Metropolitan District open solicitations:

Rocky Mountain E-Purchasing System

Reach out to Magdalena Gembal for more information: magdalena@mwcpaa.com